Client Name: NSW Pathology
Client Website: https://pathology.health.nsw.gov.au/
Client Location: Liverpool Hospital, NSW
Project Duration: 6 weeks
Reach out by phone or email or send a sample — our technical experts are ready to help!
NSW Pathology required a pass-through autoclave specifically designed for use in a PC3 (Physical Containment Level 3) environment. Maintaining full compliance with biosecurity regulations was a critical factor.
The installation site had significant space restrictions, and floor levels on either side of the pass-through differed, complicating alignment. Standard trolleys were not suitable, and any compromise would have risked barrier integrity.
A custom-built trolley system was designed to bridge the differences in floor levels, ensuring safe and seamless transfer of materials between rooms. The installation process was carefully managed to preserve the barrier seal and containment requirements.
The autoclave was successfully installed, providing a secure and compliant sterilisation solution for the PC3 facility. Barrier integrity was fully maintained, ensuring both safety and operational reliability.